What information would you make sure to have a change document ?

PlAwAnSaI

Administrator
When you receive a change document for a network change, what information would you make sure to have?

A. detailed information about the steps required to carry out the process of network change, and a rollback plan
B. an explanation of the business case for the change
C. an understanding of how long-term performance will be improved
D. a list of test cases that were conducted in the lab for this network change
bigeyes.gif
 
Top