When you receive a change document for a network change, what information would you make sure to have?
A. detailed information about the steps required to carry out the process of network change, and a rollback plan
B. an explanation of the business case for the change
C. an understanding of how long-term performance will be improved
D. a list of test cases that were conducted in the lab for this network change
A. detailed information about the steps required to carry out the process of network change, and a rollback plan
B. an explanation of the business case for the change
C. an understanding of how long-term performance will be improved
D. a list of test cases that were conducted in the lab for this network change